EU & WBs / Albania Energy Investment Updates

EU & WBs / Albania Energy Investment Updates

Presentation of Albanian Centre for Energy Regulation and Conservation - ACERC

ACERC is a think tank centre with focus on the Albania energy market and its integration in the regional IEM. The Acerc mission base on the in-depth knowledge of EU and regional energy law and policy and strives to provide a qualified contribution to the promotion of the liberalization and effective integration as well as efficient use of energy resources.

Acerc
main activities briefly consists in build-up collaborations and supports to market players in study researches such as the certificate reports, articles and periodicals. The transfer of high expertise through building-up institutional capacities by national and regional training courses, seminars and conferences. The institutional representation and integration within framework of the forum of Albanian School of Regulation.

For more visit us at the Official Website of Acerc | Albanian Energy Market - AEM Group in LinkedIn

Invitation for Expression of Interest on Consulting services “Implementation Consultant for the 400kV Transmission Line Albania-Macedonia

AEI Updates 2016Posted by Adv. Lorenc Gordani, PhD Tue, April 12, 2016 21:19:27

INVITATION FOR EXPRESSION OF INTEREST on Consulting services “Implementation Consultant for the 400kV Transmission Line Albania-Macedonia

Deadline: May 12, 2016

Country: Albania

Ref.-N°: 2010.66.992

Prequalification

Ref.: International, open Tender for engineering design and project management services (implementation consulting services) required in the construction of new and extension of existing high-voltage power transmission infrastructure in Albania

Tenderer: Operatori Sistemit Transmetimit sh.a. (OST)

Project Measures:

a) Construction of a 400 kV single circuit transmission line between Elbasan and Qafe-Thane (Albanian/Macedonian border);

b) Construction of a 400 kV single circuit transmission line between Elbasan and Fier;

c) Reconstruction and extension of 400 kV substation Elbasan 2;

d) Reinforcement and extension of 400 kV the substation Fier.

Requested Services: Implementation services required for the completion of the above measures. The estimated duration of the services is thirty-six (36) months. The services are to be provided by a team comprising of international and local long-term consultants and other professional and administrative support staff.

The prequalification of experienced Consultants is subject to the regulations contained in the “Guidelines for Assignment of Consultants in Financial Co-operation Projects” (see www.kfw-entwicklungsbank.de). The contract will be awarded to a Consultant firm fulfilling the criteria stipulated in the Invitation for Expressions of Interest, including a minimum average annual turnover in the past three years of 5 million Euros.



  • Comments(0)

Fill in only if you are not real





The following XHTML tags are allowed: <b>, <br/>, <em>, <i>, <strong>, <u>. CSS styles and Javascript are not permitted.